Over Absorption Formula
Over absorption result
because absorption rate used by the organization due to technical reason i.e.
actual information about cost is not available at time of production.
The use of predetermined
rate may result in over or under absorption. When absorbed overhead are more
than actual overheads, this is over absorption situation or case.
Over Absorption = Absorbed
overhead – Actual Overheads
Over
Absorption Formula Example
A product takes 5000 hr
machine hour. The absorption rate was $ 5 per machine hour. Actual production
overheads were $ 22,000. Calculate over or under absorption.
Absorbed
overhead
(5000
hr x 5 per hour) = $ 25,000
Less:
Actual overheard = $ 22,000
Over
absorbed = $ 3,000