Re order Level Formula
Re order level is a level at which management is
required to place new order. Re order level name itself suggest that it is a
level at which order to be placed for production.
Re order Level = Maximum usage x Maximum Lead Time
Example
8000
unit of material C is to be consumed per week
Maximum
Lead time for the stock arrival= 6 weeks
What
would be Re order level?
Solution
Re
order Level = Maximum usage x Maximum Lead Time
=
8000 x 6
=48,000 units
When
stock reaches the level of 48,000 unit, then management must consider the
placing of order to avoid any shortage.