Cost incurred Stage of completion Formula
Stage of completion can be calculated by the following
formula.
Stage
of Completion = Cost incurred to Date .
Total estimated Cost
Example
Cost
incurred = 45,000
Total
estimated Cost = 60,000
What
would be stage of completion?
Solution
Stage
of Completion = Cost incurred to Date .
Total estimated Cost
=
(45,000/60,000)
=75% (Stage of completion)