Labour
Hours Saved Example
Labour Hours saved concept
can be explained with following simple example. Labour hour saved is situation,
where standard hour more than actual hours.
Hour Saved= Expected Hour
> Actual Hour
Hour Saved = Expected Hour
– Actual Hours
Example
Labour Requirement per unit= 4 Hour
Unit to be produced=500
Actual Labour Hours = 1800
Calculate hour saved
Solution
Expected Hours = units x hour required per
unit
=500 x4
= 2000
Actual hours Spent or
taken= 1800
Hour saved= Standard hours
– actual hours
= 2000-1800
=200 Hours Saved