Labour Hours Saved Example


Labour Hours Saved Example

Labour Hours saved concept can be explained with following simple example. Labour hour saved is situation, where standard hour more than actual hours.
Hour Saved= Expected Hour > Actual Hour
Hour Saved = Expected Hour – Actual Hours

Example
Labour Requirement per unit= 4 Hour
Unit to be produced=500
Actual Labour Hours = 1800
Calculate hour saved

Solution
Expected Hours = units x hour required per unit
=500 x4
= 2000

Actual hours Spent or taken= 1800
Hour saved= Standard hours – actual hours
= 2000-1800

=200 Hours Saved