Stage of completion can be calculated by the following formula.

Stage of Completion =   Cost incurred to Date   .   
                                    Total estimated Cost

Example

Cost incurred = 45,000
Total estimated Cost = 60,000
What would be stage of completion?

Solution

Stage of Completion =   Cost incurred to Date   .   
                                    Total estimated Cost

= (45,000/60,000)
=75% (Stage of completion)