Labour Capacity
utilization Example
Labour Capacity Utilization is calculated
by the following formula. The concept of labour utilization has been explained
with an example
Labour
Capacity utilization Ratio = Hour Spent by Labour x 100
Total Available hour
Example
Hours
available for a project were = 1400
Actual
Hour Spent = 1000
What
has been Labour Capacity utilization?
Solution
Labour
Capacity utilization Ratio = Hour Spent by Labour x 100
Total Available
hour
=(1000/1400) x 100
=71.42%
This example shows that only 71.42% of total resources
available were utilized.
No comments:
Post a Comment
Note: only a member of this blog may post a comment.