Labour Capacity Utilization is calculated by the following formula. The concept of labour utilization has been explained with an example

Labour Capacity utilization Ratio =   Hour Spent by Labour   x 100
                                                  Total Available hour
Example
Hours available for a project were = 1400
Actual Hour Spent = 1000
What has been Labour Capacity utilization?

Solution
Labour Capacity utilization Ratio =   Hour Spent by Labour   x 100
                                                      Total Available hour
=(1000/1400) x 100
=71.42%
This example shows that only 71.42% of total resources available were utilized.